Workers at Embalse will carry out numerous inspection tasks, preventive and corrective maintenance, and testing and improvements. Courtesy Nucleoeléctrica.
Argentina’s Embalse nuclear power plant has begun a planned outage 24 months after the previous one, up from the usual 18-month cycle, in a change state-owned operator Nucleoeléctrica said will increase generating time while maintaining safety standards.
The 656-MW pressurised heavy water reactor (PHWR), in Córdoba province, central Argentina, came offline on 2 October after the evening peak demand period and is scheduled to return to the grid in late November.
The extension represents an increase of more than 33% in the interval between planned outages.
Want to keep reading?
Register free and get full access to NucNet for 14 days. No card required.
- Daily news briefing on the global nuclear industry
- Weekly, monthly and topical newsletters
- 24/7 coverage during nuclear incidents and safety events
- Full searchable archive, 30,000+ articles since 1991
- SMR and AMR project database
- Analysis, Focus pieces and infographics
- NucNet Style Guide for nuclear reporters and communicators
After the trial, keep a free account for a newsletter and a complimentary Plus article every two weeks. Or see our subscription plans for individuals and organisations.
See subscription options