In a report published on 11 September the National Audit Office also said the Nuclear Decommissioning Authority has incurred additional costs as a result of the failure of its original Magnox contract, with the NDA agreeing to pay up to £20m to exit the contract early.
The original contract was awarded in September 2014 to Cavendish Fluor Partnership (CFP). It was a 14-year contract to manage the decommissioning of two nuclear research sites and 10 Magnox sites.
In July 2016, the High Court ruled that the NDA had wrongly decided the outcome of the procurement process. In 2017, the NDA paid £97.3m to settle legal claims with another bidder and decided, based on legal advice, to terminate the contract with CFP nine years early.
Want to keep reading?
Register free and get full access to NucNet for 14 days. No card required.
- Daily news briefing on the global nuclear industry
- Weekly, monthly and topical newsletters
- 24/7 coverage during nuclear incidents and safety events
- Full searchable archive, 30,000+ articles since 1991
- SMR and AMR project database
- Analysis, Focus pieces and infographics
- NucNet Style Guide for nuclear reporters and communicators
After the trial, keep a free account for a newsletter and a complimentary Plus article every two weeks. Or see our subscription plans for individuals and organisations.
See subscription options