The company said it had withdrawn the application on 24 May.
On 2 May, Fennovoima announced that it had terminated the EPC contract with Raos Project, a subsidiary of Russia’s state nuclear corporation Rosatom, due to “significant delays and Raos Project’s inability to deliver the project”.
The company said at the time: “There have been significant and growing delays during the last years. The war in Ukraine has worsened the risks for the project. Raos has been unable to mitigate any of the risks.”
Fennovoima said works at the Pyhäjoki site in northern Finland related to the EPC contract have stopped. Fennovoima is now focusing on “maintaining safety and security [at the site] in the short and long term”.
Want to keep reading?
Register free and get full access to NucNet for 14 days. No card required.
- Daily news briefing on the global nuclear industry
- Weekly, monthly and topical newsletters
- 24/7 coverage during nuclear incidents and safety events
- Full searchable archive, 30,000+ articles since 1991
- SMR and AMR project database
- Analysis, Focus pieces and infographics
- NucNet Style Guide for nuclear reporters and communicators
After the trial, keep a free account for a newsletter and a complimentary Plus article every two weeks. Or see our subscription plans for individuals and organisations.
See subscription options