Nuclear Fusion / €20 Billion Iter Project At Critical Moment And Facing ‘Technical And Regulatory Difficulties’

Work continues to agree new schedule as F4E director warns MEPs of further delays

€20 Billion Iter Project At Critical Moment And Facing ‘Technical And Regulatory Difficulties’
In July 2020, the Iter project – the biggest of its kind in the world – began its five-year assembly phase. Courtesy Iter.

The €20bn ($21.9bn) International Thermonuclear Experimental Reactor (Iter) nuclear fusion project is at a critical moment and facing “technical and regulatory difficulties” as executives work to finalise a new schedule and key targets, Fusion for Energy (F4E) director Marc Lachaise told the budget committee of the European Parliament.

Lachaise said the project is experiencing “some further delays” which are temporarily affecting the full implementation of the current budget earmarked for F4E, the organisation administering Europe’s contribution to Iter.

Responding to questions from MEPs about a budget forecast for 2025-2027, Lachaise said that before a new schedule is agreed by the Iter Council, which oversees the project, it is impossible to accurately forecast figures.

Want to keep reading?

Register free and get full access to NucNet for 14 days. No card required.

Republish or license this article

MORE THAN 30 YEARS OF NUCLEAR INDUSTRY REPORTING.

Subscribe for full access to every article, the archive and the SMR and AMR database.

Join NucNet