Russia / Welding Completed Of Main Circulation Pipeline At Kursk 2-1 Nuclear Plant

Work finished 25 days ahead of schedule
Welding Completed Of Main Circulation Pipeline At Kursk 2-1 Nuclear Plant
Image courtesy Rosatom.
The welding of the main circulation pipeline has been completed for Unit 1 of the Kursk 2 nuclear power station under construction in western Russia, state nuclear corporation Rosatom said.

The pipeline connects the reactor pressure vessel (RPV) with the steam generators and the reactor coolant pumps. Welding took 55 days instead of the scheduled 80, said Rosatom.