The French state energy company EDF published the findings of a review into the cost and schedule of the two-unit power station taking account of the continuing impact of the Covid-19 pandemic.
The delay means the first EPR plant is now scheduled to start operating in June 2027, a year later than planned, with costs estimated between £25bn and £26bn. EDF said this would not affect the cost to British consumers or taxpayers, but added it assumes assuming the absence of a new pandemic wave and no additional effect of the war in Ukraine.
A reduction in the number of workers allowed on the site in Somerset due to pandemic safety measures resulted in the loss of more than half a million days of critical work in 2020 and 2021, EDF said.
Want to keep reading?
Register free and get full access to NucNet for 14 days. No card required.
- Daily news briefing on the global nuclear industry
- Weekly, monthly and topical newsletters
- 24/7 coverage during nuclear incidents and safety events
- Full searchable archive, 30,000+ articles since 1991
- SMR and AMR project database
- Analysis, Focus pieces and infographics
- NucNet Style Guide for nuclear reporters and communicators
After the trial, keep a free account for a newsletter and a complimentary Plus article every two weeks. Or see our subscription plans for individuals and organisations.
See subscription options