Hinkley Point C / UK Nuclear Power Station Delayed And Will Cost Extra £3 Billion

First of two EPR plants now scheduled to start operating in June 2027, a year later than planned
UK Nuclear Power Station Delayed And Will Cost Extra £3 Billion
March 2022 file photo of construction at Hinkley Point C, where EDF is building two EPR plants. Courtesy EDF Energy.
The new nuclear power station being built at Hinkley Point in Somerset, southwest England, will start operating a year later than planned and will cost an extra £3bn, it has been announced.

The French state energy company EDF published the findings of a review into the cost and schedule of the two-unit power station taking account of the continuing impact of the Covid-19 pandemic.

The delay means the first EPR plant is now scheduled to start operating in June 2027, a year later than planned, with costs estimated between £25bn and £26bn. EDF said this would not affect the cost to British consumers or taxpayers, but added it assumes assuming the absence of a new pandemic wave and no additional effect of the war in Ukraine.

A reduction in the number of workers allowed on the site in Somerset due to pandemic safety measures resulted in the loss of more than half a million days of critical work in 2020 and 2021, EDF said.

Want to keep reading?

Register free and get full access to NucNet for 14 days. No card required.

Republish or license this article

MORE THAN 30 YEARS OF NUCLEAR INDUSTRY REPORTING.

Subscribe for full access to every article, the archive and the SMR and AMR database.

Join NucNet