The owner and operator of the Olkiluoto-3 nuclear power plant in southwest Finland has confirmed the handover of the EPR unit from the supplier and said full commercial operation will begin on 1 May.
Teollisuuden Voima Oyj (TVO) said it had submitted a “provisional takeover certificate” to the plant supplier, the Areva-Siemens consortium, on Thursday (20 April).
“The acceptance of the plant unit ordered under a turnkey contract has today been confirmed,” TVO said. “The final acceptance of the plant unit will take place upon termination of the two-year warranty period. Even after that, the plant supplier’s liabilities under the warranty will remain in force to a certain extent for eight years at most.”
Olkiluoto-3, construction of which began in 2005 and has seen a number of delays and cost overruns, began regular electricity production on 16 April.
Want to keep reading?
Register free and get full access to NucNet for 14 days. No card required.
- Daily news briefing on the global nuclear industry
- Weekly, monthly and topical newsletters
- 24/7 coverage during nuclear incidents and safety events
- Full searchable archive, 30,000+ articles since 1991
- SMR and AMR project database
- Analysis, Focus pieces and infographics
- NucNet Style Guide for nuclear reporters and communicators
After the trial, keep a free account for a newsletter and a complimentary Plus article every two weeks. Or see our subscription plans for individuals and organisations.
See subscription options