Olkiluoto-3 / TVO Announces Further Delay Due To Problem With Turbine’s Steam Reheater

Commercial operation pushed back by about three months to December 2022
TVO Announces Further Delay Due To Problem With Turbine’s Steam Reheater
Construction of the plant began in August 2005 and is running about 10 years behind schedule. Courtesy TVO.
Test production at the Olkiluoto-3 nuclear power plant in Finland has been interrupted for more than a month causing a further delay in the start of regular electricity production at the EPR unit.

Plant owner and operator Teollisuuden Voima Oyj (TVO) said plant supplier Areva-Siemens has said regular electricity production – or commercial operation – is now scheduled for December 2022, a delay of about three months from September 2022. Test electricity production at the plant began in March.

TVO said test production had been interrupted by “foreign material issues” in the turbine’s steam reheater. In May, foreign material detached from the steam guide plates was found in the turbine’s steam reheater, which needs inspection and repair work, likely to last until the end of July.

Want to keep reading?

Register free and get full access to NucNet for 14 days. No card required.

Republish or license this article

MORE THAN 30 YEARS OF NUCLEAR INDUSTRY REPORTING.

Subscribe for full access to every article, the archive and the SMR and AMR database.

Join NucNet