Barakah Progress / Operating Licence For Unit 1 Expected Early 2020

By David Dalton
29 November 2019

Operating Licence For Unit 1 Expected Early 2020
File photo of the Barakah nuclear power station in August 2019. Courtesy Enec.
The operating licence for the United Arab Emirates’ first commercial nuclear power plant at Barakah could be issued in the first quarter of 2020, a senior official at the industry regulator said.According to Reuters, Christer Viktorsson, director-general of the Federal Authority for Nuclear Regulation (FANR), said: “If nothing new happens, it could be in the first quarter of next year, we are working towards that.” Overall construction of the four units at Barakah is more than 93% complete, Emirates Nuclear Energy Corporation said.