Flamanville-3 Reconnected To Grid After Being Taken Offline For Checks

Full power at delayed EPR in northern France scheduled for this summer

Flamanville-3 Reconnected To Grid After Being Taken Offline For Checks
Construction of Flamanville-3 started in 2007 and the plant had been initially expected to be completed in 2012. Courtesy EDF.

The Flamanville-3 EPR nuclear power plant was reconnected to the French power grid on 19 April after being taken offline on 15 February for checks and maintenance operations.

The return to the grid follows several delays related to safety inspections, reports in French media said.

The plant, which has a maximum net capacity of 1,630 MW, resumed operation at a lower level of 90 MW, owner and operator EDF said, according to reports.

Tests at various power levels are being carried out. This gradual increase in output is part of the initial startup process for the plant, a process which spans several months to comply with safety protocols.

Want to keep reading?

Register free and get full access to NucNet for 14 days. No card required.

Republish or license this article

MORE THAN 30 YEARS OF NUCLEAR INDUSTRY REPORTING.

Subscribe for full access to every article, the archive and the SMR and AMR database.

Join NucNet