Brazil / Eletronuclear Wins Appeal To Resume Construction Work On Angra-3 Nuclear Plant

City government had ordered work to stop in 2022 over ‘non accordance’

Eletronuclear Wins Appeal To Resume Construction Work On Angra-3 Nuclear Plant
Construction of Angra-3, a 1,245-MW Siemens/KWU pressurised water reactor unit, intially began in 1984. Courtesy Eletronuclear.

The Brazilian nuclear utility Eletronuclear, a subsidiary of state electricity group Eletrobras, has won its appeal before the Rio de Janeiro Court of Justice to remove an embargo on work to complete the 1,350 MW third unit of the Angra nuclear power station in Rio de Janeiro state.

Construction of Angra-3, a 1,245-MW Siemens/KWU pressurised water reactor unit, began in 1984 but was halted in 1986 because of a lack of financing.

In 2010, a construction permit was reissued by the authorities, but the project was suspended again in 2015 because of financing concerns and a corruption investigation.

Want to keep reading?

Register free and get full access to NucNet for 14 days. No card required.

Republish or license this article

MORE THAN 30 YEARS OF NUCLEAR INDUSTRY REPORTING.

Subscribe for full access to every article, the archive and the SMR and AMR database.

Join NucNet