France’s Delayed Flamanville-3 Nuclear Plant Reaches Full Power

EPR unit in Normandy scheduled for commercial operation next year

France’s Delayed Flamanville-3 Nuclear Plant Reaches Full Power
The Flamanville-3 EPR plant on th left, with the two older Flamanville units to the right. JKremona/Flamanville Nuclear Plant/Creative Commons Licence.

The long-delayed Flamanville-3 nuclear power plant in France reached 100% nuclear power at 11:37 local time on 14 December, state power utility EDF said.

EDF said in a statement that the plant, in Normandy, northern France, and had produced 1,669 MW of gross electrical power.

The increase to 100% nuclear power followed authorisation from the Nuclear Safety and Radiation Protection Authority on 12 December allowing the 80% threshold to be exceeded.

Want to keep reading?

Register free and get full access to NucNet for 14 days. No card required.

Republish or license this article

MORE THAN 30 YEARS OF NUCLEAR INDUSTRY REPORTING.

Subscribe for full access to every article, the archive and the SMR and AMR database.

Join NucNet