Flamanville-3 / Commissioning Activities Progress With Grid Connection Likely In Coming Months

‘I absolutely want us to work in complete safety and quality’, says project director

Commissioning Activities Progress With Grid Connection Likely In Coming Months
First criticality at the 1,630-MW Flamanvile-3 EPR plant is expected this year.

The Flamanville-3 EPR nuclear power plant in northern France will now undergo about seven months of commissioning activities with no clear deadline yet set for grid connection beyond a general target of later this summer.

Alain Morvan, director of the Flamanville-3 project, told a webinar organised by the French Nuclear Society (Sfen) that “I absolutely want us to work in complete safety and quality”.

Morvan said first criticality at the 1,630-MW plant is expected this year with the plant then reaching 25% of full power production, which will require approval from the regulator ASN. The plant will then need to meet final ASN regulatory requirements at 80% of full power production before reaching full power.

Want to keep reading?

Register free and get full access to NucNet for 14 days. No card required.

Republish or license this article

MORE THAN 30 YEARS OF NUCLEAR INDUSTRY REPORTING.

Subscribe for full access to every article, the archive and the SMR and AMR database.

Join NucNet