Pakistan / Cold Testing Completed For Kanupp-2 Hualong One

By David Dalton
13 December 2019

Cold Testing Completed For Kanupp-2 Hualong One
Kanupp-2 under construction. Courtesy China Nuclear Engineering Group Co.
Cold functional testing has been completed at the Kanupp-2 nuclear power plant under construction at Karachi in southern Pakistan, China National Nuclear Corporation said.The tests were completed on 2 December 2019 and involved checking more than 7,200 welds and 800 mechanical connection points for leaks at seven pressure levels, CNNC said.