Canada’s OPG Completes Installation Of Reactor Basemat For First Darlington SMR

Utility company says nuclear power plant will be first of its kind in G7 group of nations

Canada’s OPG Completes Installation Of Reactor Basemat For First Darlington SMR
The precision lift, the equivalent of lifting more than three Airbus A380 airliners, was executed by one of the world’s largest crawler cranes. Courtesy OPG.

Ontario Power Generation (OPG) has completed installation of the reactor basemat for the first unit of the Darlington BWRX-300 small modular reactor (SMR) project in Canada.

OPG said in a statement that the basemat module, weighing about around 950 tonnes and measuring about 37 metres in diameter, was lifted into place on 22 April and lowered into the reactor building shaft about 35 metres below ground.

The precision lift, the equivalent of lifting more than three Airbus A380 airliners, was executed by one of the world’s largest crawler cranes, lowering the material within millimetre precision and represents the first foundation of a new nuclear reactor to be built in Ontario in over 30 years.

According to OPG, the BWRX-300 plant will be the first SMR in the G7 group of nations.

Want to keep reading?

Register free and get full access to NucNet for 14 days. No card required.

Republish or license this article

MORE THAN 30 YEARS OF NUCLEAR INDUSTRY REPORTING.

Subscribe for full access to every article, the archive and the SMR and AMR database.

Join NucNet