The Voglte-3 and -4 nuclear power plants in the US took more than twice the estimated time to build and at more than double the cost for three main reasons, according to analysis published by Columbia University’s Center on Global Energy Policy.
Total costs for the two-unit nuclear project in the US State of Georgia have been put at approximately $35bn to $36.8bn (€31.8bn to €33.4bn) against an original budget of roughly $14bn, resulting in a delay of about seven years.
But the analysis also offered cause for optimism on future builds of the Westinghouse-supplied AP1000 nuclear plant technology, with schedules potentially becoming more reliable, the now-completed AP1000 design reducing impacts on procurement and construction, and fewer licensing issues.
Want to keep reading?
Register free and get full access to NucNet for 14 days. No card required.
- Daily news briefing on the global nuclear industry
- Weekly, monthly and topical newsletters
- 24/7 coverage during nuclear incidents and safety events
- Full searchable archive, 30,000+ articles since 1991
- SMR and AMR project database
- Analysis, Focus pieces and infographics
- NucNet Style Guide for nuclear reporters and communicators
After the trial, keep a free account for a newsletter and a complimentary Plus article every two weeks. Or see our subscription plans for individuals and organisations.
See subscription options